Square Meters Constructed in the Project : 8000 Sq.M
Scope of Works : Prime contractor for construction of Bamyan Hospital, Including HVAC, Electrical and Plumbing Works.100% procurement of Electrical and Mechanical Items were done from Overseas. (All Survey for the Project Was carried out by Raqim Team)
Start Date :10 April 2013
Completion date : 30 Sept 2016
Duration : 4 Years, 4 Months
Name and Address of Client : Aga Khan Development Network ,Afghanistan House No. 41, Street No. 2 , Qala-e-Fatullah , PO Box 5753 ,Kabul,AFGHANISTAN